Scope of Works

Construction of a 40m interlocking sheet pile wall, anchored with Stingray SR3 anchors, extending between Te Puke Highway and the Kaituna River.

  • Installing an erosion control fence and silt curtain at the base of the riverbank.
  • Clearing vegetation from the bank.
  • Temporary shoulder widening with 200mm thick AP40 aggregate over 75 metres for contra-flow traffic.
  • Saw cutting and removing pavement and concrete surfaces, and cutting steel guardrails for delivery to the NZTA yard.
  • Installing 54 x 20m SCU46-750 sheet piles, with two rows of Stingray SR-3 ground anchors (54 x 15m and 27 x 15m), including all fixings, fasteners, and grout.
  • Erecting steel whalers to the second row of anchors and conducting water jetted pile driving. Monitoring vibrations and installing an inclinometer for 12 months.
  • Installing Bidim A19 geofabric and GAP65 batter fill, with a perforated and non-perforated subsoil drainage pipe, and compacted drainage aggregate.
  • Placing GAP65 subbase and TNZ M4 AP40 basecourse, modified with cement, followed by a two-coat grade 3/5 chipseal with a membrane seal.
  • Spreading topsoil, mulch, and hydroseeding, and installing Enkamat.
  • Planting Carex Secta and NZ Flax plants.
  • Constructing a 30MPa reinforced concrete ground beam and installing a semi-rigid MASH TL3 (NCHRP 350 TL4) safety barrier system, including 6 height transition sections.

Quick Facts

  • Contract Value: $1.4M
  • Location:Te Puke Highway
  • Duration: September 2021 – October 2022

To ensure our pricing remains fair and reflects current fuel costs, we have implemented a temporary weekly review of our Fuel Adjustment Factor (FAF).

The Base rate is $1.380 per litre ex GST as at 3rd March 2026.  This rate will be recalculated each Monday and published on our website, providing customers with full visibility and transparency.

Temporary FAF Rate

Week:                   24/08/2026 – 30/08/2026

Cartage:                13.38%

Quarry:                 6.36%